News
» Go to news mainCampus Construction Update
The Campus Construction Update is a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices during summer construction.
Week of May 29th
Piping installation to continue in Chute, Boulden, Ruminant Animal Centre, Langille buildings and start in Haley and Jenkins Hall Buildings. (chance of minor noise with this work)
Civil work for concrete pads in Chute, Boulden, Ruminant, Langille, Haley and Jenkins Hall Buildings.
Electrical work to begin in Haley building. (Chance of minor noise with this work, hammer drilling)
Week of June 5th
Piping installation to continue in Langille, Haley and Jenkins Hall Buildings. (chance of minor noise with this work)
Civil work for concrete pads in Chute, Boulden, Ruminant, Langille, Haley, and Jenkins Hall Buildings.
Electrical work to continue in Haley building. (Chance of minor noise with this work, hammer drilling)
Any questions or concerns please contact:
Stephanie MacKenzie
Project Manager Facilities Management
902.956.4492
Stephanie.Mackenzie@dal.ca
Recent News
- Starting Small, Thinking Big
- Student pilipiliÂþ» at Canadian Conference
- Dal AC Queer Faculty and Staff Caucus
- WUSC Student Refugee Program
- From taking things apart to building what’s next
- Dalhousie’s third annual engagement day: Reflecting on the future of higher education
- Help out with Agricultural Campus Convocation 2026!
- Celebrate the Class of 2026 at the Grad Gala